
Recently, the Saudi Rumah 2 and Nairyah 2 projects, undertaken by Harbin Electric International (HEI), have successively achieved the significant milestone of "One Million Safe Man-Hours," marking a breakthrough in work safety for both projects and laying a solid foundation for their smooth execution.To further stimulate the enthusiasm and sense of responsibility of all personnel in work safety, the ...
As the new year began, good news came from both the Saudi Rumah 2 and Nairyah 2 project sites, undertaken by Harbin Electric International (HEI): the main structures of the 1# Electrical Control Buildings for both projects were topped out on December 29 and 31, 2025, respectively.As a core structure on the critical path of the project's ICOD, the topping-out of 1# Electric Control Building marks a ...
At 19:36 on December 7, the Indonesian Banten Power Plant Overhaul Project, executed by Harbin Electric International (HEI), achieved successful first-time grid connection and smoothly entered full-load operation. The unit completed overhaul objectives ahead of schedule, laying a solid foundation for continuous and stable power plant operation.This overhaul marks the first project executed under the ...
At 22:09 local time on December 16, the Manzanillo III 350 MW Combined Cycle Project in Mexico, constructed by Harbin Electric International (HEI), successfully achieved combined cycle grid connection and power generation. The unit is operating stably with all parameters performing well, marking a critical milestone toward full commercial operation.To ensure successful grid connection of the steam ...
On November 20, the acceptance meeting for the world’s first 300 MW/272.7 rpm pumped-storage generator-motor prototype was held in Harbin, organized by Yalong River Hydropower Development Co., Ltd. (Yalong Hydro).The prototype developed by Harbin Electric Machinery Company of Harbin Electric Corporation for the Lianghekou Pumped Storage Project underwent joint evaluation by authoritative experts from ...
From November 10 to 12, the foundation pouring for the Nairyah 2 Project 2# & 3# Gas Turbines and Generators Superstructure in Saudi Arabia, constructed by Harbin Electric International (HEI), was completed. With this milestone, the foundation pouring for all three gas turbines and generators in the main power island area of the Nairyah 2 Project has been fully completed, establishing a solid foundation ...
At 3:10 a.m. local time on October 21, the boiler blowing operation for the Manzanillo III 350 MW Combined Cycle Project in Mexico, undertaken by Harbin Electric International Co., Ltd. (HEI), was successfully completed. The target plate inspection results met all specification requirements, and the operation passed acceptance testing in a single attempt.To ensure the boiler blowing was completed on ...
At 4:00 p.m. local time on October 12, the first main girder of the 650-ton overhead crane in the main powerhouse of the Tarbela 5th Hydropower Extension Project in Pakistan—undertaken by Harbin Electric International Co., Ltd. (HEI)—was successfully hoisted into place. This milestone marks the transition of the project’s electromechanical installation into full-scale construction and signifies ...
On October 27, Jasim Husain, CEO of Abu Dhabi National Energy Company (TAQA), led a delegation to conduct an on-site inspection and research at the Nairyah 2 Project site in Saudi Arabia. Li Mo, General Manager of Harbin Electric International Co., Ltd. (HEI), along with the Nairyah 2 Project execution team, met with the delegation from the owner. Both sides engaged in in-depth discussions regarding ...
On January 24, the Dubai Hassyan project undertaken by HEI, the Unit-4 boiler first fire is successfully Done which is the key milestone of the Project.