On January 24, the Dubai Hassyan project undertaken by HEI, the Unit-4 boiler first fire is successfully Done which is the key milestone of the Project.
On January 14th, Mexico Manzanillo Phase III Project constructed by HEI, the pouring of the first pile foundation for the gas turbine is completed. All indicators are good and meet the requirements of ...
On December 22, the Amara single cycle to combined cycle expansion project, which is undertaken by HEI, the Unit 1 first synchronization with the grid is successful, and all parameters are normal and stable....
On October 6, the Pakistan BQPS III 900MW Combined Cycle Power project which is undertaken by HEI is successfully completed the HRSG boiler blowing of Unit 2, laying a solid foundation for the start-up ...
On October 1, the Turkey PM6 Project undertaken by HEI heled Commencement Ceremony for the Prefabricated unit Installation. Mr. EREN, President of the Eren Group, delivered an important speech, HEI made ...
On September 28, the Pakistan BQPS III 900MW Combined Cycle Power project, which is undertaken by HEI, the Unit 2 first synchronization with the grid is successful, and all parameters are normal and stable....
Recently, the site construction of the Dubai Hassyan Clean Coal Power Project (Project) contracted by Harbin Electric International Co., Ltd. (HEI) has achieved 7 million safe man-hours without lost time ...
Recently, units 4 and 5 of the Turkey Zetes III Power Plant, which were overhauled by HEI, were successfully synchronized for power generation with load up to 600MW. The units are working stably with all ...
On July 30, the 10KV switchgear of Unit 4 of the Dubai Hassyan Power Plant Project constructed by HEI was successfully energized, marking the successful completion of the energizing of Unit 4., The subsequent ...