
最可能的原因: IIS 收到了请求;但在处理请求过程中出现内部错误。此错误的根本原因取决于处理该请求的是哪一个模块以及出现此错误时工作进程中出现了何种情况。 IIS 无法访问网站或应用程序的 web.config 文件。...
On June 6, Unit 2 of the Dubai Hassyan 4×600MW Clean Coal-fired Power Plant Project undertaken by HEI successfully realized full-load coal-fired power generation. At present, the system parameters of Unit ...
Recently, the Thai Biomass 150MW Power Plant, which was overhauled by HEI, has successfully achieved a one-time start-up and grid connection after overhaul, and all indicators of the unit are good. ...
On Apr. 20, #1 Cooling Tower for the Pakistan Jamshoro 2X660MW Ultra-Supercritical Thermal Power Plant undertaken by the consortium of Siemens and HEI successfully topped out, marking a critical step forward ...
On April 8, HEI formally obtained the FAC issued by the owner, CELEC SUR for the Minas 3×90MW Hydroelectric Project in Ecuador, marking the final completion and the formal handover of the project. ...
On April 9 &10, the high-pressure cylinder & the intermediate-pressure cylinder of Lot #1 for Pakistan Jamshoro thermal power plant undertaken by the consortium of Siemens and HEI were successfully hoisted ...
On March 27, the final part of the main structure of the circulating water pump house renovation project of Pakistan BQPS III project undertaken by HEI began pouring. After more than 10 hours of continuous ...
On April 3, the Iraq Amara project undertaken by HEI successfully completed the hoisting of the first platform frame steel structure for No. 1 air-cooling island, marking that the air-cooling island of ...
On March 24, with the joint efforts of all parties involved in the construction the 1# and 2# steam turbine generators of the Iraqi Amara single-cycle conversion combined cycle power station project undertaken ...
On March 6, witnessed by representatives of both the owner and GE, the HEI Dubai Hassyan project successfully completed the boiler blowing of Unit 2.