On June 14, the chemical cleaning of No.2 HRSG of Pakistan BQPS III 900MW Combined Cycle Power Plant Project constructed by HEI was successfully completed, marking the completion of the erection of No....
On May 26, the No. 1 steam turbine of the Pakistan 900MW BQPS III Combined Cycle Power Plant Project constructed by HEI successfully achieved the first steam admission and SSS clutch engagement. The first ...
On April 27, the boiler hydrostatic test of Jamshoro 2×660 MW ultra-supercritical coal-fired power station project in Pakistan undertaken by HEI is successfully tested once. During the boiler ...
On March 26, the key node of the boiler blowing pipe of Unit 3 of the Dubai Hassyan project undertaken by HEI successfully completed under the witness of the owners and the representatives of GE. ...
On March 29, the temporary blow-out of No. 1 heat recovery steam generator and the hydrostatic test of No. 2 heat recovery steam generator of the BQPS III 900MW Combined Cycle Power Plant Project in Pakistan ...
On March 18, BQPS III 900MW Combined Cycle Project in Pakistan, which is constructed by HEI, Unit 1 first synchronization successfully done and began to send the first kilowatt-hour of electricity to the ...
On March 10, HEI successfully completed all the natural gas pipeline maintenance and replacement work of the DEWA’s (Dubai Electricity and Water Authority) Jebel Ali No. 2 power plant project , and successfully ...
On March 14, the BQPS III 900MW combined cycle power plant project in Pakistan undertaken by HEI, Unit 1 first fire successfully done, and all parameters are normal and stable, which marks a phased victory ...