
Recently, the site construction of the Dubai Hassyan Clean Coal Power Project (Project) contracted by Harbin Electric International Co., Ltd. (HEI) has achieved 7 million safe man-hours without lost time ...
Recently, units 4 and 5 of the Turkey Zetes III Power Plant, which were overhauled by HEI, were successfully synchronized for power generation with load up to 600MW. The units are working stably with all ...
On July 30, the 10KV switchgear of Unit 4 of the Dubai Hassyan Power Plant Project constructed by HEI was successfully energized, marking the successful completion of the energizing of Unit 4., The subsequent ...
On June 14, the chemical cleaning of No.2 HRSG of Pakistan BQPS III 900MW Combined Cycle Power Plant Project constructed by HEI was successfully completed, marking the completion of the erection of No....
On May 26, the No. 1 steam turbine of the Pakistan 900MW BQPS III Combined Cycle Power Plant Project constructed by HEI successfully achieved the first steam admission and SSS clutch engagement. The first ...
On April 27, the boiler hydrostatic test of Jamshoro 2×660 MW ultra-supercritical coal-fired power station project in Pakistan undertaken by HEI is successfully tested once. During the boiler ...
On March 26, the key node of the boiler blowing pipe of Unit 3 of the Dubai Hassyan project undertaken by HEI successfully completed under the witness of the owners and the representatives of GE. ...
On March 29, the temporary blow-out of No. 1 heat recovery steam generator and the hydrostatic test of No. 2 heat recovery steam generator of the BQPS III 900MW Combined Cycle Power Plant Project in Pakistan ...