The No. 1 unit of the Bhikki 1180MW Combined Cycle Power Station Project, Pakistan undertaken by HEI was successfully synchronized at 19:56 on March 9, 2017 local time in Pakistan and it achieved operation ...
On Feb. 22, 2017, local time 22:04, the Indonesia Banten 1×670MW Supercritical Thermal Power Plant constructed by Harbin Electric International Co., Ltd. (HEI) achieved full load generation. The boiler,...
At 7:38, Feb. 13, 2017, Indonesia local time, the Indonesia Banten 1x670MW Supercritical Thermal Power Project constructed by HEI was successfully synchronized to the Grid, laying a solid foundation for ...
Provisional Acceptance Certificate Issued for Zetas Phase III 2×660MW Thermal Power Project Time:2017-01-23 ...
HEI Successfully Achieves Synchronization of First Unit of Sudan Upper Atbara Project Time:2017-01-06 ...
HEI Invested and Contracted Dubai Hassyan Project Enters Formal Construction Phase Time:2017-01-04 ...
At 19:30 on December 10th, 2016 (local time), the auxiliary power of HEI’s Pakistan Bhikki 1180MW Combined Cycle Power Station Project, through its 500kV Switch Station, was successfully energized, and ...
On November 22nd, 2016, System B of EXTRA HIGH VOLTAGE TRANSMISSION SYSTEMS AT 500 KV AND ASSOCIATED WORKS AT 230 KV Project contracted by HEI in Ecuador was awarded the Provisional Acceptance Certificate ...
On October 3rd, 2016 (local time), the 132 km 500 kV transmission line of the B loop line at section A7 of system C of the 500 kV Extra-high Voltage Transmission Project, system C interval of the ElINGA ...