At 20:43 on June 30, Dubai local time, Unit #1 of the Dubai Hassyan 4×600MW Clean Coal-fired Power Plant Project contracted by HEI successfully realized full-load power generation. This was a milestone ...
On June 26, Dubai local time, installation of the rotor into the stator of Unit #2 and concrete pouring of the raft foundation of rows C and D of the main powerhouse of Unit #3 of Dubai Hassyan 4×600MW ...
On June 2, local time in Ecuador, HEI, the Minas-San Francisco Hydro Power Project Owner CELEC SUR, the Supervisor HIDROJUBONES and the Project’s Civil Construction Handover and Acceptance Committee officially ...
At 13:45 on May 18th, 2020, local time in Dubai, Unit 1 of Dubai Hassyan 4×600MW clean coal power plant project contracted by HEI successfully achieved synchronization at one attempt. The parameters of ...
Making an overall plan for both the epidemic prevention and control and the production and operation task is both a fierce battle and a great examination. Since the comprehensive construction and production ...
Making an overall plan for both the epidemic prevention and control and the production and operation task is both a fierce battle and a great examination. Since the comprehensive construction and production ...
At present, the COVID-19 epidemic prevention and control is in the most arduous key stage. HEI deeply implements the spirit of the important instructions given by General Secretary Xi and the decisions ...
At 12:48 AM on June 8 local time in Turkey, Unit 2 of the Turkish Soma Project was successfully synchronized for power generation for the first time, with all the system parameters of the unit being normal,...
Unit #1 of the Hassyan Project completed back feed power successfully in one shot At 16:25 on June 4 local time in Dubai, the Dubai Hassyan 4x600MW Clean Coal-fired Plant Project undertaken by HEI ...
The main truss structure of the dry coal shed at Coal Storage Yard 1 of the Dubai Hassyan Project was capped ahead of schedule At 14:00 on May 22 local time in Dubai, the Dubai’s Hassyan 4x600MW ...