
The Project, 220KV Transmission Line from Dongola to Wadi, which is contracted by our company achieved the Advance Payment from the Owner at the date of June 17th and June 29th, 2009. It indicated that ...
Along with the last instruction of operation, the circuit-breaker of generator outlet established its closing successfully at 6:38 on July 11, 2009. It indicates that the Units of 300MW Champha I Coal ...
200KV Back Feed from Grid succeeded once by 300MW Champha I Coal Fired Thermal Power Plant Project in Vietnam on July 3, 2009. The Back Feed was initially planned to be finished in October last year, however,...
At the Site of Campha II Project, 16.2 meters long and weighs 7.66 tons of boiler steel structure was hoisted and installed stably on the 50 tons of track hoist for once. This successful job indicates ...
The happy news came out from Campha I 300MW Coal Fired Thermal Power Plant in Vietnam that the Steam Turbine kept rolling 3000 Rpm for once at 16:49 on May 2. During the period of rolling and changing ...
One more happy news comes out from the site of Tuyen Quang Hydropower Project in Vietnam that the Provisional Acceptance Certificate is issued for Unit No.3 on March 13th, 2009. The Units formally entered ...
We, HPE successfully signed 2×600MW Sub-Critical Thermal Power Project Supply Contract and Service Contract for BTG Package with Coastal Energen Private limited at Indian Standard Time 2:18 on Feb 25, ...
Three Substations of Merowe Dam Transmission Lines Project achieve the Primary Transmitting for 220kv Part & 220kv Double Circuit Transmission Lines. ...
The Units of Desheng 2x300MW Coal Fired Thermal Power Plant win the Acceptance Certificates Time:2009-02-06 ...
Recently, Guangdong Desheng Project Department send back the happy news that the Unit No.2 success the 168 hours’ Trial Run and transfer to Owner for production at eighteen past nineteen on December 23rd,...