Unit No.1 of Guangdong Desheng 2×300MW Coal Fired Power Plant which was contracted by Harbin Power Engineering Company was completed 168 hours trial run at 16 o’clock on Sep. 30, 2008, and transfer to ...
Mahan 2x600MW & Salaya 2x600MW Thermal Power Plant Project in India: At present, 80% of mechanical auxiliary equipments of power plant have been purchased. Electrical auxiliary equipments are procured ...
The water test of Unit No.1 Boiler of Vietnam Campha I Project was completed successfully on 11th of August with the supervision of Client, Consultant and experts from Industry Department of Vietnam. ...
Unit No.1 was synchronized with maximum capacity of 180MW on Aug. 13, 2008, and is ready for the 168 hours trial run after necessary electrical tests. The commissioning of Unit No.2 has been started ...
Tuyen Quang 3x114MW Hydropower Project in Vietnam: Unit No.2 was put into Commercial Operation on 23rd of July. The PAC of Unit No.2 was obtained on 28th of July. The stator of generator of Unit No.3 ...
The rotor of generator of HPE Vietnam Cam Pha I 300MW Thermal Project was successful pl aced on 19th of August. By the time of this generator rotor placed, the project reached another payment ...