NEWS CENTER

Unit No.1 of Guangdong Desheng 2×300MW Coal Fired Power Plant succeed the 168 hours trial run.

source:

Page view:

Time:2008-10-07

Unit No.1 of Guangdong Desheng 2×300MW Coal Fired Power Plant which was contracted by Harbin Power Engineering Company was completed 168 hours trial run at 16 o’clock on Sep. 30, 2008, and transfer to Owner for production.

Unit No.1 achieved the full tests which required as the Station Power Construction Criterions and entered into examining for 168 hours trial run. During the period of examining, the running parameter, related systems and CBTC (coordinated boiler-turbine control) have achieved and exceeded the requirements of Design Examining. The oscillation index of major equipment was choiceness and other indexes were choiceness too.

TOP