Mahan 2x600MW & Salaya 2x600MW Thermal Power Plant Project in India:

At present, 80% of mechanical auxiliary equipments of power plant have been purchased. Electrical auxiliary equipments are procured stage by stage. The design institute is doing the general drawing and it will be finished in this month. The order of main equipments, such as boiler, turbine and generator, have completed.

Jharkhand 2x600MW & Salaya II 2x600MW Thermal Power Plant in India:

The Advance Payment of Salaya II Project was received on 22nd of July and it means the contract of Salaya II Project become effective. The technical agreements of main equipments of subjected projects were signed already, and the commercial contract will be signed recently.