On October 21st 2008, the Vietnam Campha I Coal Fired Thermal Power Plant successfully established high pressure casing, intermediate pressure cylinder and low pressure casing, which indicated that the Turbine Body installation has basically finished.
For the safety of Casing Covering work, site people of the Campha I Project Department examine and approve the report with Installation Company, the Owner and Supervision Company, and the parties re-measure the key data of Turbine Flowing Equipment. Before the starting suspend, the relative persons make all the suspend tools keep safety. The cooperation between all project parties, the Supervision Company supervises at site, and the Project Department leader present at the work site for casing of Turbine covering, based on these above advantages, the casing covering favorably established.
Being based upon the controlling of construction person, the high pressure casing, intermediate pressure cylinder and low pressure casing are falling on the Turbine Inner Equipment steadily.
This successfully Milestone Point establish a steadily advancement for the complete period of the Vietnam 300MW Campha I Coal Fired Thermal Power Plant Project and final electricity production