Bin Qasim CCPP successfully passed 240 hours reliability test run of combined cycle on the 1st try

source:

Page view:

Time:2012-05-08

At 12:00 a.m.,April 28,2012, Bin Qasim 560MW CCPP constructed by Harbin Electric International Company has successfully passed 240 hours reliability test run of combined cycle on the 1st try. During the period, each system was in a good status and production system put into operation. Generating electricity was with full designed capability in the condition of the remote operation.

Now, project is preparing for the performance test of combined cycle and making full preparation for taking over combined cycle plant.