The concrete pouring of the steam turbine foundation of the Jamshoro project in Pakistan was successfully completed

source:

Page view:

Time:2020-12-09

After 20 hours of continuous operation, the concrete pouring of the Unit 1 steam turbine operating layer platform of Pakistan’s Jamshoro 2×660MW ultra-supercritical coal-fired power plant project undertaken by HEI was successfully completed at 4:20 on December 5, with a total concrete pouring volume of 990 cubic meters.