NEWS CENTER

The Units of 300MW Champha I Project win the first successful Synchronization

source:

Page view:

Time:2009-07-14

Along with the last instruction of operation, the circuit-breaker of generator outlet established its closing successfully at 6:38 on July 11, 2009. It indicates that the Units of 300MW Champha I Coal Fired Thermal Power Project win the first successful Synchronization. The commissioning person started evaluating work of the technical indexes of the plant after synchronization, and the result is so expected. The nice synchronization is a symbol of full conditions for further power generation and foreshows an upcoming completion of the Project.


TOP