200KV Back Feed from Grid succeeded once by 300MW Champha I Coal Fired Thermal Power Plant Project in Vietnam on July 3, 2009. The Back Feed was initially planned to be finished in October last year, however, due to the problems of transmigrant EVN was keeping out from Grid and not approach principle on time. Based on the hard working of all site staffs, 200KV started delivery of current in two days of July 2nd and July 3rd, and the whole progress was established in an orderly way.
This Milestone point as a symbol brings the Project entering into the final step of Startup and Commissioning. After finishing Commissioning work the Project shall finally succeed synchronization.