source:
Page view:
Time:2020-10-09
At 9:00 on October 6th, local time, the concrete pouring work for the foundation of the Unit 4 heat recovery steam generator of Iraq Amara project undertaken by HEI was successfully completed, which took 13 hours. The successful completion of the pouring work opened up a new milestone for the localization of the Iraq project, and also laid a solid foundation for the subsequent steel structure hoisting.