By October 29, 2011, the 3# gas turbine of Bin Qasim 560MW power project completed 24 hour full load and 240 hours reliability test run at a time. This is another great milestone for third single cycle power station since the 2# and 1# completed their test on September 24 and October 25, 2011.
So far, the completion test including performance test and 240 hours reliability test for 3 units of gas turbines were finished successfully, main body of gas turbines and its auxiliaries can operate steady, the Bin Qasim 560MW power project has the condition of generation power for single cycle power station.