Hydraulic Pressure Test for 2# Boiler of 300MW Cam Pha II Coal-Fired Thermal Power Plant |
Time:2010-06-23 |
A good news came from the Site of Cam Pha Project that the Hydraulic Pressure Test for 2# Boiler has passed in one time at 16:30 dated on May 14th , 2010. The test press of water wall, super heater, economizer and drum is 29.8MPa, the test press of Re-heater is 7.5 MPa. The test was carried out with the supervision of Owner and Consultant. Also the result satisfied the ASME standard and relevant requirements for running. The success for this important milestone indicates the completion installation of the heat parts of 2# boiler of 300MW Cam Pha II Coal-Fired Thermal Power Plant and makes good foundation for the coming commissioning works. |