A good news came from the Site of Cam Pha Project that the Hydraulic Pressure Test for #1 Boiler has passed in one time at 17:20 dated on March 6th , 2010. The test press of water wall, super heater, economizer and drum is 29.7MPa, the test press of Re-heater is 7.5 MPa. The test was carried out with the supervision of Owner and Consultant. Also the result satisfied the ASME standard and relevant requirements for running.
The 720 hours reliability running was passed on Feb 1st ,2010. This time the success for this important milestone has refresh the score of Cam Pha Project. And the success indicates the completion installation of the heat parts of 1# boiler of 300MW Cam Pha II Coal-Fired Thermal Power Plant. and makes good foundation for the coming works. We believe that Cam Pha Project will refresh the good score under the hard work of the staff of HPE and subcontractors of Cam Pha Project.