On April 12, 2026, local time in Mexico, the performance test for the 350MW Manzanillo III Combined Cycle Power Plant, undertaken by Harbin Electric International (HEI), successfully passed acceptance inspection. This marks a critical step towards the project’s full commercial operation. In the presence of the owner, supervisors, and representatives from various parties, the unit operated stably with ...
On March 30, He Song, Minister-Counselor of the Chinese Embassy in Saudi Arabia, and his delegation visited the Rumah 2 project site for inspection and guidance, and carried out a field survey of the construction site and the living quarters camp.He Song and his delegation visited the construction site and the living quarters camp, where they inspected the project's construction status and the employees'...
From March 31 to April 1, Li Chao, Chairman of the Board of HEI, led a team to conduct a site inspection at the Syrdarya II Project in Uzbekistan. During the visit, the team inspected the project's construction progress, listened to reports on project execution, and set forth requirements for the next phase of work.Li Chao fully affirmed the remarkable achievements made by all employees at the Syrdarya ...
At 17:30 on April 4, local time in Mexico, the Manzanillo III 350MW Combined Cycle Power Plant Project, constructed by HEI, successfully completed its 15-day reliability run. The unit operated steadily with excellent parameters, demonstrating reliability that exceeded contract and dispatch requirements. This marks another significant milestone after the completion of various complex grid-related dispatch ...
Safety is an unwavering core value at Harbin Electric International (HEI). In November 2025, a road traffic accident occurred on Highway 6465—the very road that project employees travel daily for their commute and that serves as the main route for transporting materials to and from the site. The incident put the Nairyah 2 project team on high alert, reinforcing the conviction that the responsibility ...
At 13:58 on March 29, local time in Saudi Arabia, 1# Gas Turbine for the Saudi Nairyah 2 Project, constructed by Harbin Electric International Company Limited (HEI), was successfully positioned, marking the start of the installation work for the unit and laying a solid foundation for the project's subsequent progress.As the "heart" of the entire combined-cycle power plant, the gas turbine requires ...
On March 25 and 28 local time in Saudi Arabia, the first steel structure lifts for the heat recovery steam generators (HRSGs) at the Nairyah 2 and Rumah 2 projects—both contracted to Harbin Electric International (HEI)—were successfully completed. The milestone marks the formal entry of the HRSG areas at both projects into the intensive equipment installation phase, laying a solid foundation for ...
On March 26, Independent Non-Executive Directors of Harbin Electric Company Limited, He Yu, Niu Xiangchun, and Gao Yibin, visited Harbin Electric International (HEI) for an inspection visit, receiving briefings on the company's operational development, the strategic planning during the 15th Five-Year Plan, and the execution of overseas project construction, and putting forward guidance and requirements ...
The Nairyah 2 project of Harbin Electric International (HEI) is located in a typical inland desert climate zone characterized by harsh natural conditions—extreme heat, persistent drought, and frequent sandstorms year-round. Confronted with the vast, barren desert landscape surrounding the site, the Nairyah 2 project team recognized that creating a healthy, comfortable, and livable working and living ...
At 22:00 local time on March 23, Gas Turbine Unit 2 of the Syrdarya II 1,600 MW Combined Cycle Power Plant Project in Uzbekistan, contracted by Harbin Electric International (HEI), was successfully fired up for the first time. The milestone marks another stage victory in the construction of what is currently the largest combined cycle power plant under construction in Central Asia, and stands as one ...