On October 31, the HEI project team started the construction of the first pile foundation at the storage tank area of the Liquefied Natural Gas (LNG) project in the West Port Area of Yantai Port, which marked the official start of construction of the receiving station for the LNG project.
LNG project is the first project that HEI entered the field of oil and gas. The project is located in the West Port District of Yantai Port, Yantai City, Shandong Province. The scope of the contract mainly includes the design, supply, construction, commissioning and takeover of the LNG receiving station project (excluding the supporting port project and the first station project). The project will be mechanically completed on April 30, 2023, and reach production on January 31, 2024.