The pouring work of the main structure of the refurbishment project of the circulating water pump house of the Pakistan BQPS III project has been completed

source:

Page view:

Time:2021-04-12

On March 27, the final part of the main structure of the circulating water pump house renovation project of Pakistan BQPS III project undertaken by HEI began pouring. After more than 10 hours of continuous fighting, the pouring work was successfully completed, with a total pouring volume of 350 cubic meters, It marks the beginning of the installation phase of the refurbishment project of the circulating water pump house.