Good news came from Paiton Site, Indonesia that back feeding for Paiton Coal Fired Steam Power Plant (1×600MW) succeeded at 16:25 on April 21, 2010 and all the equipments run regular after being energized. Until 17:47, April 22, 2010, all the tests for this back feeding were accomplished smoothly. Success of this mile stone signified commissioning phase has already come to Paiton Project in the whole way.